Tuesday, May 01, 2007

April 30, 2007

With a little planning and a lot of phone calls we're getting started this week. Trent will be coming out to dig the foundation down the rest of the way and dig the footings and drains and maybe the trenches for the well and septic. He'll also build the road around to the basement door and to the septic. Kenny will be there with Donnie to make sure it all goes smoothly.

We should be able to start the basement the next week and the septic and well can come in at their own convenience as long as they stay out of the foundation guys' way.

0 Comments:

Post a Comment

<< Home